Bankhead
Owner: Alabama Power
Location: Black Warrior River, Alabama
Size: 5.89 m
Power: 54 MW
Net Head: 20.12 m
Scope of Work:
- New Runner
- New Wicket Gates
- New Head Gates
- New Stop Logs
- New trash rack guide rails
- New Powerhouse door (wider for new one piece runner)
- New grease system including bronze bushing and wear pads.
- New servo, bearing, water, air and brake piping.
- New HPL system
- Rehabilitated Headcover
- Rehabilitated Bottom Ring
- Rehabilitated Linkage
- Rehabilitated Gate Ring
- Rehabilitated Thrust and guide bearings
- Rehabilitated Servo motors
- Complete Scroll case concrete surface repair by clan and coating
- Refurbished and reset stator sole plates including concrete repairs, required lifting of stator
- Refurbish and re-coat trash racks
- Rehabilitated Generator and Turbine shaft